Bathroom renovation electrical in NZ: what to plan and when

The lights, extractor fan, heated towel rail, mirror lighting, switches, power points and underfloor heating to decide before work starts, and when each stage is done.

Updated 2026-11-13

Bathroom renovation electrical in NZ: what to plan and when

The electrical work in a bathroom renovation is planned from the new layout before work starts: our list sets out every light, the extractor fan, the heated towel rail, the lighting at the mirror, each switch and power point, and any underfloor heating, each with its position. Cables go in while the walls and ceiling are open, and the fittings are connected once the tiles and vanity are in. Our kitchen and bathroom electrical work follows that order.

Lights and mirror lighting

Ceiling lights are placed from the layout, but joists, ducts and pipes in the ceiling space decide where a downlight can go, so each position is checked in the ceiling space or on site at rough-in. Decide which switch controls each light, and choose any dimmer with the fittings: an LED fitting dims properly only with a dimmer that suits it.

At the vanity, the light can be a fitting over the mirror or a backlit mirror, and its supply is placed at the mirror position while the wall is open. Our bathroom renovation album shows both: a light over the mirror, and backlit oval mirrors above the vanity.

The bathroom extractor fan

Clause G4.3.3 of the Building Code requires buildings to have a means of collecting or otherwise removing moisture from bathing and showering from the spaces in which it is generated. Clause G4 sets out the performance required, not fan sizes.

The fan's position is chosen with its duct: the route to the point where the air leaves the building. Where the duct passes through the roof or an outside wall, the opening and its weatherproofing are agreed before the work is booked. The fan can be switched with the light, on a switch of its own, or with a run-on timer that keeps it running for a set time after it is switched off. Each option is wired as part of our extractor fan installation.

Older heat, light and fan units

In a 2022 safety warning, WorkSafe noted a number of fires involving older combination bathroom heat, light and fan units made before 2008 by several brands that use plastic lamp holders for the heat lamps, which are known to deteriorate over time. It recommends checking these units visually, with the power to the unit turned off first. If one shows scorching, melting plastic, burn marks, abnormal flickering, unusual smells or arcing noises, WorkSafe's advice is to stop using it immediately and have a licensed electrical worker replace it. We replace these units.

Heated towel rail and underfloor heating

A heated towel rail and any underfloor heating are decided at the planning stage, so their wiring goes in with the rest. Mark the towel rail on the layout, and where you want its switch; one photo in our album shows a heated towel rail with its switch and controller.

Electric underfloor heating, a heating mat or cable under the tiles, is planned with the tiler: it is laid on the open floor around the vanity, bath and shower, and the floor height and the order of work are agreed before the mat goes down. The thermostat goes on a wall that is easy to reach, with its cable in before the linings. The mat or cable is tested before it is covered and again after tiling; see electric underfloor heating.

Switches, power points and RCDs

Switches and power points move to suit the new vanity, shower and mirror positions, and the position of each point near the bath and shower is checked before it goes on the list.

WorkSafe says RCDs should be installed in damp areas of the home where there are electric fittings, such as bathrooms, and that it is a legal requirement for all new circuits from the switchboard supplying lighting or socket-outlets in domestic buildings to have RCD protection. An RCD constantly monitors the current on its circuit and shuts off immediately if it senses a loss of current. A new point goes on an existing circuit nearby or a new circuit from the switchboard, and a new circuit needs room on the board; if there is none, a switchboard upgrade is listed and quoted with the bathroom work.

When the electrician comes in during a bathroom renovation

StageWhenWhat happensWhat you decide
Plans and quoteBefore work startsEvery point listed from the layout: what stays, what moves and what is newThe fittings and the switching; you confirm the list and the quote
Rough-inWalls and ceiling open, before the liningsCables run to every position, including the thermostatFinal positions, checked on site
Linings and floorBefore stopping and tilingUnderfloor heating tested once laidA change now means opening a wall or ceiling
Fit-offTiles and vanity inLights, fan, towel rail, mirror, switches and power points connectedFittings on site, with their instructions
Testing and certificatesEnd of the jobCircuits and lights tested before the room is handed back; the certificates issuedHandover

Take photos of every wall before the linings go up. They show where the cables run, which helps anyone fixing a vanity, mirror or towel rail to those walls later. The power is off only while circuits are connected or changed, at times agreed with you in advance.

What to send for a quote

  • the bathroom layout or plans, with the vanity, mirror, shower, bath and towel rail positions
  • the fittings you have chosen and their installation instructions: lights, mirror, fan, towel rail, and any underfloor heating with the floor finish
  • photos of the room and the ceiling, and of the outside wall or eaves near where the fan will go
  • a photo of the switchboard with its door open
  • the builder's programme, showing when the walls and ceiling will be open
  • any asbestos test result: WorkSafe says a home built before 1 January 2000 may contain some asbestos materials

FAQ

Can I supply my own mirror or fan?

Yes. Send the model and its installation instructions before the list is confirmed, so its supply is placed at rough-in, and have it on site before fit-off.

What if the old wiring has a problem once the walls are open?

It is recorded with what it needs and priced as its own item. You decide before anything beyond the confirmed list is done. WorkSafe's warning signs for the rest of the house are set out in does my house need rewiring.

Can the builder or bathroom company do the wiring?

Only if the person doing it is a licensed electrical worker: WorkSafe says only a licensed electrical worker can carry out work on another person's home or do work for payment, reward or koha. EWRB, the Electrical Workers Registration Board, suggests checking that an electrical worker's licence has not expired, and searching the public register to confirm it has not been suspended.

Will I get a certificate?

Yes. WorkSafe says electricians must issue a Certificate of Compliance for any fixed wiring work, including new power points, and you also receive an Electrical Safety Certificate once the work is connected. WorkSafe calls the Certificate of Compliance an important document that may be required when you sell the home.

Send an online enquiry or call with the address and what you need. Email plans or photos to info@adamelectrical.co.nz.

Enquiry Call 022 159 8899