Electrical test results sheet in NZ: the required testing

Prescribed electrical work must be tested, and the person connecting it must be satisfied that the testing has been done (Electricity (Safety) Regulations 2010, rr 63, 73A).

Updated 2026-11-13

The testing is required; the sheet is the record

An electrical test results sheet, often called an electrical test sheet or a commissioning test sheet, is the written record of the tests done on an installation and what they found. The Electricity (Safety) Regulations 2010 (ESR) require the testing (ESR r 63). On a Certificate of Compliance (COC), test results are optional additional information (ESR r 67(3)).

What the regulations require about testing

All prescribed electrical work on a low or extra-low voltage installation must be tested (ESR r 63(1)):

  • for operational safety
  • to ensure the installation is not electrically unsafe
  • as regulation 59 or 60 requires
  • for an installation that does not comply with Part 2 of AS/NZS 3000, by the verification or testing process in its certified design

Failing to test is an offence (ESR r 63(3)). Prescribed electrical work on a high-voltage installation is tested under regulation 38 (ESR r 64).

Until the close of 12 November 2026, a person who complied with the standard the regulations cited before 13 November 2025 was treated as complying (ESR Sch 1AA cl 1(2)). WorkSafe's note on the change says the cited standard changes to AS/NZS 3000:2018, including Amendments 1, 2 and 3, and that new installations whose construction begins after 12 November 2026 must comply with it. WorkSafe counts the design phase as construction, so work whose quote or tendering process was already under way by 12 November 2026 can be done to the old standard. WorkSafe adds that the old version of the standard can still be used for repair work, and that where a repair moves into alterations or additions, that work must comply with the newly cited standard.

Testing and the COC

The person issuing a COC states that they are satisfied the work was done lawfully and safely (ESR r 66(1)(a)). "Lawfully and safely" includes that the testing the regulations require has been satisfactorily completed (ESR r 66(2)(b)).

Test results are not a required field on the COC. The regulation says the issuer "may include any additional information (such as testing results)" on the certificate (ESR r 67(3)). The fields a COC must record are listed in COC vs ESC.

Testing required before connection

Before connecting a low or extra-low voltage installation on which prescribed electrical work has been done, the person doing the connection must be satisfied that it is safe to connect and that the testing the regulations require has been done (ESR r 73A(1)(a), (b)). Where a COC is required, they issue one or sight one issued no earlier than 6 months before connection (ESR r 73A(1)(c)). If the person connecting did not do the testing personally, they must sight documentation, signed by the person who did the tests, that sets out what tests were carried out and what the results were (ESR r 73A(3)). Under the Electricity Act 1992 (EA), the work must not be connected until the testing, certification and inspection the regulations require have been carried out (EA s 82(1)). Inspection applies to high-risk work, one of the three categories in prescribed electrical work (ESR r 70).

Testing in the regulations at a glance

ProvisionWhat it says
ESR r 63(1)All prescribed electrical work on a low or extra-low voltage installation must be tested
ESR r 63(3)Failing to test is an offence
ESR r 64Work on a high-voltage installation is tested under regulation 38
ESR r 66(2)(b)"Lawfully and safely" on a COC includes the required testing being satisfactorily completed
ESR r 67(3)Test results may be included on a COC as additional information
ESR r 73A(1)(b)The person connecting must be satisfied that the required testing has been done
ESR r 73A(3)A person connecting who did not do the tests must sight signed documentation of the tests and their results
EA s 82(1)No connection until the required testing, certification and inspection are carried out

Why a written commissioning test sheet is useful

The regulations require the testing. A written sheet is how the results last beyond the day of the test:

  • The issuer of a COC signs that the required testing has been satisfactorily completed (ESR r 66(2)(b)); the sheet is the record behind that signature.
  • Results added to the COC as additional information go out with the certificate (ESR r 67(3)), and a copy of every COC is kept for at least 7 years (ESR r 74E(3)); see keeping certificate records.
  • When a meter installer, lines worker or inspector does the connection, that person completes the ESC (WorkSafe) and must be satisfied the testing has been done (ESR r 73A(1)(b)). Because they did not do the tests, they must sight signed documentation of the tests and their results (ESR r 73A(3)); a test sheet signed by the person who did the tests, listing the tests and results, is that documentation.
  • A question months later about one circuit is answered from the sheet, not from memory.

FAQ

Do test results have to be on the COC?

No. They are not a required field. The issuer may include them on the certificate as additional information (ESR r 67(3)).

What must be tested?

All prescribed electrical work on a low or extra-low voltage installation: for operational safety, to ensure the installation is not electrically unsafe, and as regulation 59 or 60 requires (ESR r 63(1)).

Does signing a COC confirm the testing?

The issuer states the work was done lawfully and safely (ESR r 66(1)(a)), and that includes the required testing having been satisfactorily completed (ESR r 66(2)(b)).