How long to keep COC records in New Zealand

COCs, ESCs and Records of Inspection are each kept for at least 7 years, in hard copy or electronically (Electricity (Safety) Regulations 2010, rr 72A, 74E, 74G).

Updated 2026-11-13

Seven years for every certificate

How long to keep COC records is set by the Electricity (Safety) Regulations 2010 (ESR): a copy of every Certificate of Compliance (COC) is kept for at least 7 years, in hard copy or electronically (ESR r 74E(3)). The same applies to Electrical Safety Certificates (ESCs) and Records of Inspection (RoIs) (ESR rr 74G(1)(b), 72A(1)(b)). What each certificate certifies is set out in COC vs ESC.

Who keeps what

RecordWho keeps the copyHow long
COCThe person who issued it, or the holder of the employer licence if it was issued under one (ESR r 74E(1), (3))At least 7 years
ESCThe person who issued it (ESR r 74G(1)(b))At least 7 years
RoIThe person who issued it (ESR r 72A(1)(b))At least 7 years

A COC has attached to it any manufacturer's instructions, supplier declarations of conformity (SDoCs) and certified designs used in the work, or it says where they can be found electronically (ESR r 66(1)(d), (3)). Test results may be added to the COC as additional information (ESR r 67(3)); see the commissioning test sheet. RoIs come from the inspection of high-risk work (ESR rr 70–72), one of the categories described in prescribed electrical work.

Copies for the client and the owner

Each document has its own deadline:

  • COC: within 20 days after completing the work (ESR r 74E(2))
  • ESC: within 20 working days after it is issued (ESR r 74G(1)(a))
  • RoI: within 20 working days after it is issued (ESR r 72A(1)(a))

Copies go to the person who contracted for the work or, if that person is not readily available, to the owner or occupier (ESR rr 74E(2), 74G(1)(a), 72A(1)(a)). Since 15 January 2026, for work on a non-consented small stand-alone dwelling, the COC and the ESC go to both the person who contracted for the work, if readily available, and the owner of the dwelling (ESR rr 74E(2A), 74G(1)(a)).

Requests for a copy: 10 working days

The keeper of a COC, ESC or RoI must supply a copy within 10 working days of a request from any of these (ESR rr 74E(4), 74G(2), 72A(2)):

  • WorkSafe
  • the Electrical Workers Registration Board (EWRB)
  • the Registrar
  • the territorial authority
  • the person who contracted for the work
  • the owner or occupier of the place where the installation is

Breaking the COC and ESC record rules is an offence (ESR r 74H). The EWRB also treats certification failures as a disciplinary matter (Electricity Act 1992 s 143(f); EWRB notice).

Paper or electronic

The regulations accept copies kept in hard copy or electronically (ESR rr 74E(3), 74G(1)(b), 72A(1)(b)). WorkSafe accepts emailing certificates and filing them electronically. A certificate can also be part of another document, such as an invoice, if it is clearly identifiable (WorkSafe certificate templates).

A record checklist for each job

  • the COC, the ESC and any RoI for the job, kept together
  • the date the work was completed, which starts the 20-day COC period (ESR r 74E(2))
  • the date the ESC was issued, which starts its 20 working days (ESR r 74G(1)(a))
  • who received each copy, and when
  • the manufacturer's instructions, SDoCs and certified designs attached to the COC, or where they are online (ESR r 66(1)(d), (3))
  • a copy that can be found and sent within 10 working days of a request (ESR r 74E(4))

FAQ

How long must a COC be kept?

At least 7 years, in hard copy or electronically, by the person who issued it or the employer-licence holder (ESR r 74E(1), (3)).

Do ESCs and Records of Inspection follow the same rule?

Yes. Each is kept for at least 7 years by the person who issued it (ESR rr 74G(1)(b), 72A(1)(b)).

Who can ask for a copy, and how quickly is it due?

WorkSafe, the EWRB, the Registrar, the territorial authority, the person who contracted for the work, and the owner or occupier. The copy is due within 10 working days of the request (ESR rr 74E(4), 74G(2), 72A(2)).

Can certificates be emailed and kept electronically?

Yes. Electronic copies meet the 7-year rule (ESR r 74E(3)), and WorkSafe accepts emailing certificates and filing them electronically.

When does the client receive the COC?

Within 20 days after the work is completed (ESR r 74E(2)). The ESC follows within 20 working days after it is issued (ESR r 74G(1)(a)).