An electrical variation order records a change to the agreed scope: a point added, moved, changed or removed after the client confirmed the list and the quote. A variation needs something to vary from, so it starts with the room-by-room list the client confirmed at the client walkthrough. Without that list, a change is one person's memory against another's.
What counts as a variation
- a point added: an extra socket, more downlights, a new data point
- a point moved after its position was confirmed, in particular after rough-in
- a point removed, which reduces the price
- a changed type: a single socket becomes a double, a fixed light becomes dimmable
- work the plans did not show: an appliance circuit, outdoor lighting, a run to an outbuilding
- a return visit caused by a change
Anything on the confirmed list is not a variation, however it is described later.
How a variation runs
- The change is requested. Note who asked, when, and in what words.
- Find it on the confirmed list: the room, the point, the quantity before and after.
- Price it from your catalogue, including any extra visit it causes.
- Send it to the person who approves changes: what, where, how many, the price excl and incl GST, and any effect on timing.
- Wait for written confirmation before doing the work.
- Do the work and update the list, so the job record shows what was built.
- Invoice it as agreed: with the next progress invoice, or on its own.
Who approves changes is agreed at the start of the job. On a new build that may be the owner, the builder or both. The variation goes to that person, whoever asked for the change.
What a variation order shows
| Field | Example |
|---|---|
| Number and date | VO-03, and the date it was issued |
| Requested by | The name of the person who asked |
| Location | Kitchen, island bench |
| Change | Add one double socket |
| Work type | Supply and installation |
| Quantity | 1 |
| Price | From your catalogue, excl GST, then GST at 15% |
| Confirmed by | Name, date, and how: signature or email |
Price variations from a catalogue
A catalogue is a list of the items you add most often, each with a set price for each kind of work: pre-wire only, installation only, supply and installation. Pricing from it means:
- a variation can be priced on site, while the client is there
- the same item costs the same on every job and for every client
- the price can be explained by pointing at the catalogue line
Timing changes the work. Moving a point before rough-in is a change on the plan. Moving it after the linings are up means opening the wall or ceiling, and someone has to make good the lining afterwards. Price the later change for the work it takes, and state on the variation who makes good.
Timing changes credits too. A point removed before rough-in comes off at its full price. A point removed after its cable is run has already used rough-in time and cable, so the credit covers only what is not yet done: the fit-off, and the switch, socket or fitting.
Confirm before the work
Extra work done before it is confirmed is work the client has not agreed to pay for. Confirming first means:
- the client knows the price before it is spent
- the final invoice contains nothing the client has not already approved
- the builder's programme and the client's budget can both be updated
When a change comes up on site and the wall is about to be lined, send the variation by message or email with a photo of the location, and get the reply before doing the work.
FAQ
Is a removed point a variation?
Yes. Record it against the confirmed list like any other change, with the reduction in price, and have it confirmed.
Should small changes be recorded too?
Yes. One moved socket is recorded the same way as a large change. A small change left off the record has nothing to be checked against when the final invoice arrives.
Does the client have to sign every variation?
Each variation needs a written confirmation from the person who approves changes. A signature on the variation or a reply by email both give you that record.
What if the builder asks for the change?
Send the variation to whoever approves changes on that job, as agreed at the start. A request from the builder is priced and confirmed the same way.
How are variations invoiced?
On separate lines from the original price, either with the next progress invoice or on their own, so the quote and the changes can both be checked.